In Paraguay, complaints about public tenders do not go to the body that ran the tender. They go to the public procurement authority, the Dirección Nacional de Contrataciones Públicas (DNCP), as a protesta (Law 7021/2022, Art. 127). The law leaves the deadlines to DNCP regulations, and once they expire the right to protest is lost.
Two deadlines, two targets
- Against the tender conditions (the pliego de bases y condiciones or an addendum): from publication until the third working day before the bid opening in open tenders, and until the second working day in small-value tenders (licitaciones de menor cuantía), national or international. The opening day is not counted, and the reference is the opening date in force when the challenged document was published, even if the opening is later postponed (DNCP Resolution 234/2025, Art. 58, as amended by Resolution 3955/2025; current text in the DNCP regulatory digest).
- Against the result: within 7 working days of notification of the decision (Art. 59, as amended). In two-envelope procedures, a protest against the technical qualification must also be filed by the third working day before the price envelopes are opened.
A worked calendar
The examples assume that no public holiday falls within the period; each holiday pushes the dates back by one working day.
- Result notified on a Monday. The count starts the next day: Tuesday is day 1, Wednesday day 2, Thursday day 3, Friday day 4, Monday day 5, Tuesday day 6. Wednesday of the following week is day 7, the last day to file.
- Open tender with bids opening on a Thursday. Counting back without the opening day, Wednesday is the first working day before, Tuesday the second and Monday the third. Monday is the last day to protest against the conditions. In a small-value tender the last day is Tuesday.
The contracting body cannot sign the contract until the protest period has run out (Decree 2264/2024, Art. 105).
What stops the clock and what does not
- It does not stop: asking the contracting body for an informative hearing (audiencia informativa, Decree 2264/2024, Art. 86).
- It stops: requesting the evaluation report when the body notified the result without delivering it in full, including requests for clarification of bids, the answers and the attachments. The suspension runs from the request until the body hands over what was missing, and the protest must include the documents that prove it (Resolution 234/2025, Art. 59, as amended).
- It does not stop either: a question on the conditions that the body has not answered (Art. 56, as amended).
What the protest must prove
- Standing: documents proving the signatory's power of representation, filed with the first submission (Resolution 234/2025, Art. 55).
- Interest in challenging the conditions: proof that the point was first raised as a question through the procurement portal (SICP), with a copy of the question, the publication confirmation or a screenshot, or an explanation of why the question could not be asked; plus a tax registration (RUC) certificate or municipal licence showing a line of business that matches the tender (Art. 56, as amended).
- Interest in challenging the result: the bidder must have taken part in the procedure and justify its interest expressly (Art. 57).
- Timeliness: if the act and its notification are not published in the SICP, the protest must include the documents showing it was filed on time (Art. 59).
After filing
- The DNCP admits or rejects the protest within 5 working days of filing. Grounds for rejection at the threshold include lack of standing, lack of legitimate interest, late filing, a manifest lack of grounds and an improper object (Law 7021, Art. 128).
- An admitted protest suspends the procedure at whatever stage it has reached, under the personal responsibility of the protester. The contracting body can ask to continue within 3 working days of notification of the protest; the DNCP rules within 3 working days, and silence counts as refusal (Art. 129).
- The DNCP decides within 35 working days, counted from the day after it opens the protest proceedings (Art. 128). It can annul the act or the procedure, issue guidelines to put the procedure back on track, or reject the protest (Art. 130).
- Reconsideration can be requested within 3 working days (Resolution 234/2025, Art. 90). In protest cases it does not suspend the effects of the decision (Law 7021, Art. 155). The ruling on reconsideration closes the administrative stage and opens the way to the administrative courts (Art. 156).
Common mistakes
- Waiting for a meeting with the contracting body before filing: the hearing does not stop the 7 days.
- Challenging a requirement of the conditions without having asked about it before the question deadline; the deadlines are in the e-tender calendar.
- Filing without the power of attorney or the RUC certificate: both lead to rejection at the threshold.
Guarantees and payment terms for the winning bidder are covered in our guide to guarantees and payment, and the rules for foreign companies in bidding from abroad. The wider picture is on the Paraguay country page.
Sources
- Law No. 7021/2022 on Public Supply and Procurement, Arts. 127-130, 155 and 156 (DNCP, PDF)
- DNCP Resolution No. 234/2025 on legal procedures and protests, Arts. 55-60 and 90 (PDF)
- DNCP regulatory digest of Law No. 7021/2022, Decree No. 2264/2024 and DNCP resolutions, including Resolution No. 3955/2025, January 2026 (PDF)