Paraguay's public tenders run on the portal of the public procurement authority, the Dirección Nacional de Contrataciones Públicas (DNCP), known as the SICP. For a company planning its first bid, two things decide how much time is really left: the regulatory calendar and the steps of the electronic bid module.
Before the call: register and access
- Supplier Register: registration is a precondition for bidding, and a supplier counts as registered when it has an active administrator user (DNCP Resolution 2939/2024, Arts. 2 and 8). The DNCP checks the documents within a maximum of 4 working days from the day after the application; if it raises an observation, the count starts again once the error is corrected (Arts. 9 and 10).
- Access to the module: an active user in the Register, the permission to load and submit bids if the user is a secondary one, a security PIN generated from the user profile, and the mandatory documents kept up to date. Each bidder designates a legal representative to sign and submit electronic bids, and the user name and password count as an electronic signature (DNCP Resolution 232/2025, Art. 2).
The calendar
- Minimum publication, in calendar days before the opening: open tender 15 (national) or 30 (international); small-value tender (menor cuantía) 9 (national) or 15 (international). The contracting body can set longer periods (DNCP Resolution 230/2025, Art. 39).
- Questions: through the SICP, until the fourth working day before the opening in open tenders and the third in small-value tenders (Art. 50).
- Answers: by the third working day before the opening in open tenders and the second in small-value tenders (Art. 51). The body cannot open bids without answering every question received in time (Law 7021/2022, Art. 49).
- Addenda changing the conditions: published at least 6 working days before the opening in open tenders (Resolution 230/2025, Art. 52).
- Opening: public, no more than 30 minutes after the submission deadline (Decree 2264/2024, Art. 70).
A worked calendar
An international open tender with bids opening on a Thursday, assuming no public holiday falls in the period:
- Publication: at least 30 calendar days before that Thursday.
- Last addendum changing the conditions: Wednesday of the previous week, the sixth working day before the opening.
- Last day for questions: Friday of the previous week, the fourth working day before.
- Last day for answers and for a protest against the conditions: Monday, the third working day before (protest rule: DNCP Resolution 234/2025, Art. 58, as amended).
- Thursday: submission deadline, opening within 30 minutes, then 60 minutes for bidders to review the other bids (Resolution 232/2025, Art. 11).
- Award: within 20 calendar days of the opening, extendable once for the same period; after that, bidders may withdraw their bids without consequences (Decree 2264/2024, Art. 83).
Loading the electronic bid
The DNCP guide for suppliers sets out the sequence:
- Find the tender ID in the tender search engine, open the call and select Presentar oferta electrónica.
- Fill in the menus while the bid stays in draft: bid data; products, goods and services, where prices can be imported from the Excel template as a CSV file; documents; linked contracts; guarantees; authorised users; and the bid form.
- Under documents, upload files or link those already in the Supplier Register. The register profile certificate (constancia de perfil) is not accepted in place of the documents themselves.
- Under guarantees, load the insurance policy, the bank guarantee with a qualified electronic signature or, in small-value tenders, the sworn statement generated by the module.
- Generate the bid form, accept the sworn statement on the terms, then sign and submit.
The bid cannot be submitted without the substantial documents, and international bidders must upload proof of an address or a local representative in Paraguay (Resolution 232/2025, Art. 4).
Confidentiality, changes and the opening
- Confidential documents: the bidder must name the legal rule that protects them; otherwise the whole bid is public (Resolution 232/2025, Art. 8). A confidentiality claim without legal basis can be sanctioned (DNCP guide).
- Withdrawing or changing: possible until the opening date and time (Art. 6). A withdrawn bid goes back to draft and must be confirmed and sent again (DNCP guide).
- Review after opening: 60 minutes to examine the other bidders' documents and record observations; the body can extend the period (Art. 11).
Common mistakes
- Registering after spotting the tender: an observation restarts the 4 working days.
- Withdrawing a bid to correct it and not sending it again.
- Attaching the register profile certificate instead of linking the documents.
- Missing the question deadline: a protest against the conditions has to show that the point was asked about first. The deadlines are in our guide to protests.
The guarantees and payment terms are covered in guarantees and payment, and the extra requirements for foreign companies in bidding from abroad. More on the country on the Paraguay page.
Sources
- DNCP Resolution No. 230/2025 on procedures, Arts. 39 and 50-52 (PDF)
- DNCP Resolution No. 232/2025 on electronic bids, Arts. 2, 4, 6, 8 and 11 (PDF)
- DNCP Resolution No. 2939/2024 on the State Supplier Register, Arts. 2 and 8-10 (PDF)
- Law No. 7021/2022 on Public Supply and Procurement, Art. 49 (DNCP, PDF)
- DNCP regulatory digest of Law No. 7021/2022, Decree No. 2264/2024 (Arts. 70 and 83) and DNCP resolutions, January 2026 (PDF)
- DNCP Resolution No. 234/2025 on legal procedures and protests, Art. 58 (PDF)
- DNCP, electronic bidding guide for suppliers