Before pricing a bid for a Paraguayan public body, a company needs to know how much cash the contract ties up and when the money comes back. The rules are in Law 7021/2022 and its implementing Decree 2264/2024, published together with the DNCP resolutions in the DNCP regulatory digest.

Cash tied up

  • Bid guarantee (garantía de mantenimiento de oferta): 5% of the total bid (Law 7021, Art. 51). It takes the form of a bank guarantee from a bank established in Paraguay and authorised by the Central Bank of Paraguay, or a surety policy from an insurer authorised to operate in Paraguay. If the bidder agrees to extend the validity of its bid, the guarantee has to be extended too (Decree 2264/2024, Art. 74). In procedures estimated below 2,000 minimum daily wages (jornales mínimos) a sworn statement is accepted instead (DNCP Resolution 230/2025, Art. 7).
  • Performance guarantee: 5% to 10% of the total contract (Law 7021, Art. 71), delivered within 10 calendar days of signing the contract, or before delivery if the goods, services or works are due within that period. The forms are the same: a bank established in Paraguay or an insurer authorised in Paraguay (Decree 2264/2024, Art. 119).
  • Studies, technical projects and works supervision (the law's consultoría category, Art. 3): no performance guarantee, but professional liability insurance for 10% of the contract (Art. 71).
  • Works: 5% of each payment is withheld as a repair fund (fondo de reparos), without interest, and returned within 10 calendar days of final acceptance; that term can be extended to a maximum of 30 calendar days. If the tender conditions allow it, an insurance policy can replace the fund (Art. 71).

Cash coming in

  • Advance: up to 30% of the contract, to finance start-up costs, amortised during performance and covered by a guarantee for 100% of its value (Law 7021, Art. 62). The tender conditions set the percentage, the request deadline and the amortisation, and the advance cannot be changed by amendment (Decree 2264/2024, Art. 111). The advance guarantee can be reduced each year to the balance still owed (Art. 119). In multi-year contracts the advance is only paid for the first fiscal year (Law 7021, Art. 62; Decree 2264/2024, Art. 112).
  • Payment terms: set by each contract (Law 7021, Art. 62); the law fixes no single number of days.
  • DNCP contribution: 0.4% of every invoice or works certificate, net of taxes, withheld by the contracting body (Art. 63).
  • Before every payment: a valid tax compliance certificate (Certificado de Cumplimiento Tributario) and social security contributions up to date (Decree 2264/2024, Art. 114).

A worked example

A works contract won with a bid of PYG 1,000,000,000 (guaraníes), with the same amount as contract value:

  • Bid guarantee: 5% of 1,000,000,000 = PYG 50,000,000, in place from the day of the bid.
  • Performance guarantee: between PYG 50,000,000 (5%) and PYG 100,000,000 (10%), depending on the rate in the tender conditions, within 10 calendar days of signing.
  • Maximum advance: 30% = PYG 300,000,000, against a guarantee for PYG 300,000,000.
  • A payment of PYG 200,000,000: the repair fund withholds 5% = PYG 10,000,000. If the certificate amount net of taxes is also PYG 200,000,000, the DNCP contribution is 0.4% = PYG 800,000.

Late payment

  • More than 60 calendar days late: the supplier can ask in writing to suspend performance. The contracting body must reply within 10 working days from the day after it receives the request; silence counts as refusal, which closes the administrative stage and opens the way to the administrative courts (Decree 2264/2024, Art. 120; Law 7021, Art. 66).
  • More than 120 calendar days late: the supplier can suspend performance, giving the contracting body one month's notice. Payment of the full debt restores performance (Decree 2264/2024, Art. 120; Resolution 230/2025, Art. 198).

What to prepare before bidding

  • A bank or insurer in Paraguay able to issue the bid guarantee before the deadline, on the proforma in the tender conditions. In electronic bids, a bank guarantee must carry a qualified electronic signature (DNCP Resolution 232/2025, Art. 5).
  • A credit line for the performance guarantee, due 10 calendar days after signing.

Common mistakes

  • Calculating the guarantee on the wrong base: in open contracts by quantity, the 5% applies to unit prices multiplied by the maximum quantities; in open contracts by amount, to the maximum amount (Decree 2264/2024, Art. 64; Resolution 230/2025, Art. 45).
  • Not signing in time: the contract must be signed within 15 working days of notification of the award; otherwise the award can be revoked and the bid guarantee called (Decree 2264/2024, Art. 105).
  • Letting the performance guarantee run out: in open contracts it must cover 30 calendar days beyond the end of the contract, and be extended if the contract is (Art. 64).

Deadlines for challenging an award are in our guide to protests, and the steps of the electronic bid in the e-tender guide. Rules for foreign companies are in bidding from abroad. More on the country on the Paraguay page.